Home / Project fact file

Project fact file

The installation of 72 Nordex N149/5.x MW turbines – with a hub height of 105 metres and a rotor diameter of 149 metres – uses the very latest wind turbine technology and provides renewable energy with no CO₂ emissions and the least possible impact on the surrounding natural environment.

Øyfjellet Wind Park will annually produce around 1.3 TWh. This is enough energy for 39% of Alcoa's annual electricity needs, or for 82,500 households, around 178,200 people – corresponding to 73% of everyone who lives in Nordland.

Annual expected production is based on many years of weather data collected from measurement masts placed in the area. For wind power, it is common practice to calculate P50, P75 and P90 figures. At ØWAS, the calculations are: P50 indicates 1.3 TWh, P70 indicates 1.2 TWh, P90 indicates 1.14 TWh.

Aluminium producer Alcoa, Mosjøen's cornerstone industry, has purchased all power produced by the wind park for 15 years. This guarantees opportunities for growth and helps safeguard hundreds of Norwegian jobs.

The Municipality of Vefsn covers an area of 1,849 km². The licenced area covers 40 km², around 2% of the municipality. Roads, turbines and buildings cover roughly 2–3% of the licenced area.

Timeline

2023
The project was taken over
Øyfjellet Wind AS took over the wind park from the developer.
2022
All turbines put into operation
2021
72 turbines installed
MTA plan approved
The Ministry of Petroleum and Energy approved the environmental, transport and construction plan (MTA) for the development.
Municipal council approved the agreement
The municipal council in Vefsn unanimously approved the agreement on 17 June – the municipality receives NOK 422.5 million over the 25-year concession period.
2020
Construction begins
Construction of internal roads, crane pads and turbine foundations.
Transmission line and switchgear construction
132 kV transmission line and switchgear between Marka substation and the wind park.
Objection review from NVE
NVE decided not to uphold the objections to the MTA plan – the assessments complied with the regulations. The case was sent to the Ministry for a final decision.
2019
Detailed plans approved
The environmental, transport and construction (MTA) plans are submitted, designed to ensure the least invasive development possible. Øyfjellet is removed from the planning area following local input. Approved by NVE in December 2019.
Contractor and suppliers selected
Veidekke selected as main contractor. Linka selected for the transmission line, Helgeland Kraft for grid connection, Nordex for turbines.
2018
Long-term power agreement
15-year agreement for all wind power produced to go to Alcoa in Mosjøen.
Capacity
NVE grants a licence for 400 megawatts of capacity.
2016
Final permit
The Ministry of Petroleum and Energy grants final permission for the project.
2014
Application and municipal support
The licence application is submitted and the municipal council in Vefsn gives its support. The Øyfjellet area around Stortuva is not developed, following dialogue with the local community.
2011
Joining forces on the project
Local landowners and industry join forces on the project to bring more green power to industry.